Bond Hill – 2024 Street Preventive Maintenance

 

STREET DISTANCE TREATMENT START DATE END DATE
Bellavista Street Reading Rd to East End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/30
05/21
06/03
Carrahen Avenue Newfield Ave to Reading Rd Micro-Surfacing 05/16 05/18
Carrahen Court Carrahen Ave to South End Micro-Surfacing 05/16 05/18
Catalina Avenue Rhode Island Ave to West End Micro-Surfacing 05/30 06/03
Cheyenne Drive West End to Towanda Ter Micro-Surfacing 05/30 06/03
Coad Drive Lois Dr to Rosemore Dr Micro-Surfacing 05/16 05/18
Elm Park Drive Paddock Rd to West End Micro-Surfacing 05/16 05/18
Elm View Place Towanda Ter to South End Micro-Surfacing 05/17 05/20
Hermit Avenue Andina Ave to Dalewood Pl Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/30
05/21
06/03
Lois Drive Paddock Ave to Coad Dr Micro-Surfacing 05/16 05/18
Newfield Avenue Dale Rd to North End Micro-Surfacing 05/30 06/03
Phantom Avenue Andina Ave to Dalewood Pl Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/30
05/21
06/03
Rockingham Avenue Rhode Island Ave to End of Subdivision Micro-Surfacing 05/16 05/18
Towanda Terrace Paddock Rd to West End Micro-Surfacing 05/17 05/20

*Dates are subject to change due to weather and field conditions.

**Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.