Mt. Auburn – 2024 Street Preventive Maintenance

 

STREET DISTANCE TREATMENT START DATE END DATE
Albion Place Auburn Ave to Gilman Ave Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/23
05/21
05/24
Alvin Street Dorchester Ave to North End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/23
05/21
05/24
Bodmann Avenue Auburn Ave to Alvin Ave Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/23
05/21
05/24
Earnshaw Avenue West End to East End Micro-Surfacing 05/23 05/24
Gilman Avenue Maplewood Ave to Auburn Ave Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/23
05/21
05/24
Ryan Avenue Dorchester Ave to North End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/23
05/21
05/24
Slack Street Highland Ave to Young St Cape Seal – SAMI
Cape Seal – Micro-Surfacing
05/18
05/23
05/21
05/24
Valencia Street Rice St to Valroy Pl Micro-Surfacing 05/23 05/24

*Dates are subject to change due to weather and field conditions.

**Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.