Queensgate – 2025 Street Preventive Maintenance
| STREET | DISTANCE | TREATMENT | START DATE | END DATE |
|---|---|---|---|---|
| 5th Street | Gest St to Linn St | Micro-Surfacing | 09/30 | 10/02 |
| 6th Street | Gest St to Linn St | Micro-Surfacing | 09/30 | 10/02 |
| 7th Street | East End to Carr St | Micro-Surfacing | 09/30 | 10/02 |
| Carr St | Dalton Ave to 8th St | Micro-Surfacing | 09/30 | 10/02 |
| Gest St | Mehring Way to 3rd St / Linn St | Micro-Surfacing | 09/30 | 10/02 |
| Gest St | 3rd St / Linn St to Linn St Ramp (West) | Pavement Repair | 09/30 | 10/02 |
| Gest St | Dalton Ave to Western Ave | Pavement Repair | 09/30 | 10/02 |
*Dates are subject to change due to weather and field conditions.
**Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.