Queensgate – 2025 Street Preventive Maintenance

 

STREET DISTANCE TREATMENT START DATE END DATE
5th Street Gest St to Linn St Micro-Surfacing 09/30 10/02
6th Street Gest St to Linn St Micro-Surfacing 09/30 10/02
7th Street East End to Carr St Micro-Surfacing 09/30 10/02
Carr St Dalton Ave to 8th St Micro-Surfacing 09/30 10/02
Gest St Mehring Way to 3rd St / Linn St Micro-Surfacing 09/30 10/02
Gest St 3rd St / Linn St to Linn St Ramp (West) Pavement Repair 09/30 10/02
Gest St Dalton Ave to Western Ave Pavement Repair 09/30 10/02

*Dates are subject to change due to weather and field conditions.

**Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.