Camp Washington – 2022 Street Preventive Maintenance

 

STREET DISTANCE TREATMENT START DATE END DATE
Arlington Street Spring Grove Ave to Colerain Ave Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022 10/3/2022 9/21/2022 10/5/2022
Avon Place Meeker St to Spring Grove Ave Crack Seal
Micro-Surfacing
9/7/2022 10/3/2022 9/9/2022 10/5/2022
Cook Street Draper St to Straight St Crack Seal
Micro-Surfacing
9/7/2022 10/3/2022 9/9/2022 10/5/2022
Draper Avenue Cook St to Spring Grove Ave Crack Seal
Micro-Surfacing
9/7/2022 10/3/2022 9/9/2022 10/5/2022
Ethan Avenue Colerain Ave to Spring Grove Ave Crack Seal
Micro-Surfacing
9/7/2022 10/3/2022 9/9/2022 10/5/2022
Garrard Street Hopple St to Elam St Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022 10/3/2022 9/21/2022 10/5/2022
Meeker Street Hopple St to Avon Pl Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022 10/3/2022 9/21/2022 10/5/2022
Monmouth Street Spring Grove Ave to Colerain Ave Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022 10/3/2022 9/21/2022 10/5/2022
Sidney Avenue Marshall Ave to North End Crack Seal
Micro-Surfacing
9/7/2022 10/3/2022 9/9/2022 10/5/2022

 

*Dates are subject to change due to weather and field conditions.

*Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.