STREET DISTANCE TREATMENT START DATE END DATE
Airy Ct Monfort Hills Ave to East End Micro-Surfacing 10/19 11/06
Chesterfield Ct Shadymist Ln to East End Micro-Surfacing 10/19 11/06
Foxglove Ln Goldenrod Dr to West End Micro-Surfacing 10/19 11/06
Goldenrod Dr Colerain Ave to Little Flower Ave Micro-Surfacing 10/19 11/06
North Raeburn Dr Raeburn Dr to North End Micro-Surfacing 10/19 11/06
Raeburn Ln Raeburn Dr to South End Micro-Surfacing 10/19 11/06
Raeburn Tr Raeburn Dr to North End Micro-Surfacing 10/19 11/06
Whitewood Ln East End to West End Micro-Surfacing 10/19 11/06

*Dates are subject to change due to weather and field conditions.