Northside – 2022 Street Preventive Maintenance

 

STREET DISTANCE TREATMENT START DATE END DATE
Badgeley Street Martha St to South End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022
10/4/2022
9/21/2022
10/6/2022
Martha Avenue Kirby Rd to Badgeley St Crack Seal
Micro-Surfacing
9/8/2022
10/4/2022
9/10/2022
10/6/2022
Northview Avenue Stanford Dr to East End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022
10/4/2022
9/21/2022
10/6/2022
Thompson Heights Avenue Glen Parker Ave to East End Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/19/2022
10/4/2022
9/21/2022
10/6/2022

*Dates are subject to change due to weather and field conditions.

*Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.