Walnut Hills – 2022 Street Preventive Maintenance

 

STREET DISTANCE TREATMENT START DATE END DATE
Altoona Street Walter Ave to Kerper Ave Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/20/2022 10/7/2022 9/22/2022 10/10/2022
Chapel Street East End (NR Victory Pkwy) to Ashland Avenue Crack Seal
Micro-Surfacing
9/12/2022 10/4/2022 9/14/2022 10/6/2022
Francis Lane Victory Pkwy to Park Ave Crack Seal
Micro-Surfacing
9/12/2022 10/7/2022 9/14/2022 10/10/2022
Gaff Avenue Beresford Ave to North End Crack Seal
Micro-Surfacing
9/12/2022 10/7/2022 9/14/2022 10/10/2022
Laredo Avenue McMillan St to Cypress St Cape Seal – SAMI
Cape Seal – Micro-Surfacing
9/20/2022 10/7/2022 9/22/2022 10/10/2022
May Street Pavt. Change north of Oak St. to South End Micro-Surfacing  10/7/2022  10/10/2022
Walter Street Gilbert Ave to North End

Crack Seal                                 Micro Surfacing

9/13/2022 10/8/2022 9/15/2022 10/11/2022

 

*Dates are subject to change due to weather and field conditions.

*Prior to Micro-Surfacing treatments, a product (Crack Seal) will be applied to repair pavement cracks, as noted in the schedule.